Update Jan 13

Building  activity still centers around infrastructure, and this week is concentrating on the septic system.

We expect to have the septic system permit by mid-January which then must be sent to SAWS (septic system can’t start until we have permanent water on the site.)

After we have SAWS approval of the water main extension, we can submit the Overall Plans and application to City of San Antonio for Building Permit submission and review.

Architect thinks that realistically we are 5 to 6 weeks from construction.

 